Commissioning and Performance Testing

Before Start-up

Verify airflow balance, filter installation, and that controls (bypass, frost, alarms) are configured.

Measure On Site

  • Supply and exhaust airflow
  • Inlet and outlet temperatures on both streams
  • Pressure drop across the core

Calculate Effectiveness

Use the measured temperatures to compute actual effectiveness and compare it with the rated curve at the same conditions.

Document

Keep the commissioning sheet with the O&M manual. It is the baseline for future troubleshooting and verifies the savings claim.