The Building
A refrigerated warehouse, -25 C inside, frequent door traffic, warm make-up air needed for defrost and personnel doors.
Step 1 - Duty
Make-up air 6,000 m3/h, outdoor summer 30 C, indoor -25 C; the load is refrigeration, not heating.
Step 2 - Technology
Plate core sized for low face velocity, with a defrost strategy for the cold intake.
Step 3 - Frost
Below -2 C exhaust dewpoint, add a preheat coil or timed bypass set from the coldest week, not the average.
Step 4 - Result
Pre-cooling incoming air trims refrigeration energy by 10 to 25 percent depending on door traffic and climate.